logo
logo

Flexible Storage When Needed: A Mobile Warehouse in Morocco

Mobile Warehouse in Morocco
Table of Contents

Project Overview

Project Type:
Mobile Warehouse
Client:DAWEC Wind Farm
Built Duration:16 Days
Structure Type:A-Frame Structure with Aluminum Alloy Frame
Location:Dakhla, Morocco
Temporary Warehouse Structure in Morocco

Project Background

Dakhla DAWEC Wind Farm required a dedicated storage space for storing materials on site. Rather than simply adding more storage capacity, the project also needed to consider on-site operations, access to the space, and potential future relocation. These factors would allow the storage space to suit the site conditions and operational needs better.

Based on these requirements, a mobile warehouse was selected as a practical temporary storage building. It provides around 320 m² of storage space and can be relocated when needed. The setup keeps the storage space from being limited to a fixed location and provides greater flexibility for site operations. So, how does the warehouse achieve this mobility? The next section looks at its structure and mobile system.

Temporary Warehouse Storage Solution

What Makes This Warehouse Flexible?

The flexibility of this mobile warehouse comes from its integrated movement system. Dedicated tracks are installed at the bottom of the structure, allowing the entire warehouse to move along a set path through the drive system. The tracks control the movement direction and range, while the drive system provides the power needed to adjust the warehouse position based on site requirements.

Compared with structures that need to be dismantled, moved, and reassembled by hand, this design reduces the time and labor required for repeated installation work. Operators do not need to move individual frames or take the structure apart. The entire warehouse can be controlled through the driving system. For a wind farm that needs to keep its temporary warehouse storage in use, this automated movement can reduce disruption to site operations and make storage space management easier.

Flexible Storage System for Wind Farm
Mobile Warehouse Storage Space

The mobile function is not provided by a single additional component. It relies on the combined performance of the main frame, track system, and drive system. Each part is accurately positioned and coordinated during installation, allowing the warehouse to move smoothly along its set path while keeping the storage space intact. The combined setup gives the wind farm a flexible storage system that can better adapt to changes in site operations.

Project Installation and Quality Control

For a mobile warehouse, site installation involves more than assembling the main structure. The movement system also needs to work accurately with the entire structure. At the Dakhla DAWEC Wind Farm project, the installation followed a planned process from site preparation to final handover, with each stage focused on structural stability and reliable movement.

Site Preparation and Mobile Warehouse Installation

Installation began with site preparation. The team surveyed and checked the installation area at Dakhla DAWEC Wind Farm to confirm that the site met the installation requirements. Traffic and material loading routes were also planned in advance to reduce disruption during material transport. All delivered materials were checked and counted to make sure every component needed for installation was ready.

Temporary Storage Building Installation
Once the site was prepared, the team moved on to the main installation work. Setting out was completed first, followed by track positioning and installation for the mobile system. The main aluminum frame was then assembled, followed by the beige roof and gable fabric coverings. After the main structure was completed, the drive system was installed to connect the tracks, frame, and drive unit, giving the entire warehouse its mobile function.
Drive System Installation
Frame Positioning

Structural and Safety Checks Before Handover

After the main installation of the mobile warehouse was completed, the team carried out pre-handover checks on the structure and fabric to assess its condition for normal use. The first check focused on the vertical alignment of the entire structure to confirm that the aluminum frame was installed accurately and remained stable.

Bolts, pins, and other fasteners were then checked one by one to make sure all connections were secure with no missing or loose parts. The fabric tension was also inspected to ensure the beige fabric was smooth and properly tensioned.

Warehouse Frame Vertical Alignment Check
Fastener Inspection

These checks covered the structural installation and connection details and provided a solid basis for the warehouse to operate properly. Once all inspections were completed and the requirements were confirmed, the storage space was ready for formal handover and use at Dakhla DAWEC Wind Farm.

Project Result

The project was completed and put into use within 16 days, providing Dakhla DAWEC Wind Farm with a complete on-site storage space. Pre-handover checks covered the structural vertical alignment, fasteners, and fabric tension. The warehouse met the requirements for use, while the track and drive systems kept the space mobile.

The project combines storage capacity with a mobile design, giving the site more than a fixed storage area. Its position can be adjusted based on actual needs. Shelter Structures has also delivered temporary warehouse structures for projects in Chile and Taiwan, with solutions adapted to different site storage needs.

These projects demonstrate Shelter Structures’ experience in on-site installation and customized flexible storage solutions. If you need flexible storage space for your project, contact us for a mobile warehouse solution tailored to your needs.

Contact Us

Make On-Demand Space Solutions Easier, Faster  

SHELTER has a great team of skilled architects ready to support your project or Event at any time.

When you’re ready to start your next business, get in touch with us now, and our architects will get back to you with a quote as soon as possible.

Business Email

      admin@shelter-structures.com

United States Office

+1 713-386-9281

VALENCIA, CALIFORNIA 27788 Hancock Pkwy Valencia, CA 91355

China Office

+86 13928858552

NO.1 Huanghe Section, Songshan Road, Chao Tian Industrial Zone, Shilou Town Panyu District, Guangzhou

You can upload files
CLICK ON THE BUTTON OR DRAG& DROP FILES
Upload Files
Drag files here or browse for
the above files